Thanks for answering Ahmet.
Yeah, That does it, I went searching and found this thread too:
http://www.primaveratools.com/Forum...fault.aspx I guess I just didn't understand what the "schedule" button actually does. I see now that you can make it run during any schedule changes or only when you hit F9
May I ask besides Paul Harris' book do you know of any good tutorial resources for someone like me? I'm trying to build a schedule for a project that has already been started; it was built in MS Project and was converted to P6.
All the activities and wbs have been built, but not all the relationship lines have been put in so I'm afraid that if I run the schedule it's gonna mess things up.
Guess I'll export it with a different name, import it back in and mess around. I imagine I'll be on this board quite a bit. But if anyone has any starting points on this I would be very thankful.