I exported two connected project. Then, one is imported to another computer. It is noticeable that start date of activities connected to the other project have asterisk. In my understading this is a mark if there a constraint applied in the activities. But, when I checked Activity Details, under Status tab, I could not see any constraint applied in the activities in question. Is there any way to eliminate the asterisk sign? See the attached file.
This helps. Thank you very much.Â
I really tried to attached the file but I don't really know what went wrong why it did not appear on the sent message .Â